Counted backwards from the morning your crew walks onto the floor. Every task has a free version and an expensive version, and the only difference is the month.

A custom exhibit under construction in a fabrication shop
Every task has a free version and an expensive version. The difference is the month.

It is still early is the most expensive sentence in exhibiting. Here is what is actually due, counted backwards from the morning your crew walks onto the floor.

NPE runs every three years, which changes the planning maths in a way people underestimate. There is no next one in eight months to absorb a mistake. Whatever you build has to work, and whatever you miss you carry for three years.

The timeline below is generic on purpose. Attach it to the real dates the moment PLASTICS publishes the exhibitor kit, and let the earliest hard deadline pull everything else forward.

The fixed point is Monday May 3, 2027, when the doors open at the Orange County Convention Center. Behind it sits the move-in window, which opens Thursday April 22 and runs to Sunday May 2. Count backwards from those two dates, not from the show alone.

Nine months out: decide what the booth is for

Not what it looks like. What it is for. A booth built to run a machine in front of buyers is a different building from one built to hold twelve private meetings a day, and the two briefs produce different floor plans, different budgets, and different staffing.

This is also when you decide the honest question: rent or build. For a first US show at 10 x 10 or 10 x 20, rental usually wins. Above 20 x 20, or if you exhibit in the US more than once a year, building and storing tends to cost less by the second show. The arithmetic is in rent or buy your exhibit, and it is worth running before you brief anybody.

Eight months out: booth number, and what it tells you

Your booth number is not just a location. It tells you your booth type, which determines your display rules, your hanging sign eligibility, and how many finished elevations you are paying for. It tells you which building you are in. It tells you your neighbours, your aisle, and whether there is a column in your space.

Read the floor plan against the booth, not just the booth against the floor plan. A corner is an opportunity and a column is a constraint, and both change a design more than most people expect.

Seven to six months out: design and approval

Concept, then 3D renders, then construction drawings. The render is the thing you approve and the thing you should get, which is why we put the render next to the built booth on the NPE2027 page rather than describing it.

If you are running equipment, the machine has to enter the design here, not later. Its footprint, height, weight, utility draw, guarding, and service access are inputs to the floor plan. A design that treats the machine as furniture to be placed afterwards gets rebuilt on install day, on your budget. The five constraints that decide a machinery layout are set out on the live machinery page.

Six to five months out: engineering and the first hard deadline

Structural and electrical drawings. Island booth submissions for show management review. Hanging sign approval, which is commonly the earliest deadline in the whole kit and is a permission rather than a purchase: past the date, the answer is no.

This is the point where a design decision made in month nine either holds or does not. If you want a sign, the shape of that sign has to be settled several months before anybody hangs it.

Five to four months out: fabrication starts, and freight gets real

Fabrication begins. In parallel, the international freight conversation has to start, because it has the longest and least controllable lead time on the whole list.

If equipment is coming from outside the US, the customs route has to be chosen now. An ATA Carnet has to be opened before the equipment ships, not after it lands, which is the single most common and most expensive scheduling mistake international exhibitors make. See ATA Carnet or temporary import bond.

Three months out: order everything in the kit

Electrical, compressed air, water and drainage, rigging, internet, cleaning, furnishings, labor. All of it, against the advance deadline, in one sitting.

Specify electrical placement on the floor plan while you are there. The drop goes where you say. Say nothing and it goes somewhere convenient for the contractor.

File your exhibitor appointed contractor paperwork in the same week: notice of intent, certificate of insurance. Late paperwork does not cost extra, it stops your crew at the door.

Two months out: graphics, and the freight decision

Graphics production files and color proofing. This is the last comfortable moment to change a message, and the last moment at all to change it cheaply.

Advance warehouse or direct to show. Advance costs more per hundredweight but your crates are in your space when you arrive. Direct is cheaper and puts you at the mercy of the marshalling queue on the day. For a build with a tight install window, advance is usually the cheaper decision once you count a crew standing idle. The trade-off is unpacked in drayage, explained.

One month out: the dry build

Build the booth in the shop before it goes in a crate. Not a mock-up, the actual booth, assembled by the people who will assemble it in the hall.

This is where you find the panel that does not sit flush, the graphic that is two inches short, and the sequence problem nobody spotted in a drawing. Every one of those is cheap to fix in a shop in Orlando and expensive to fix on a show floor at 7 a.m.

It is also where the install crew learns the build, which is the actual reason it matters.

Move-in week

The machine lands first and the booth closes around it. Utilities get connected and tested before the structure makes them unreachable. Graphics go on last so they are not being leaned against for two days.

Then the part nobody plans: dismantle. It is six hours that decide whether your booth survives to the next show, and it is the shift where a booth built to be reused either gets packed properly or gets packed fast.

What this timeline is really for

Every entry above has a version that costs nothing and a version that costs money, and the only difference between them is which month you did it in. None of it is difficult work. It is just work that has an order.

Nine months is not a long time. It is thirty six weeks, and four of them are already spent.